Perhaps December 19, 1978, December 8, 1999, or November 4, 2006, or November 4, 2006, do not mean anything in particular to you. However, during each of these dates, France experienced a situation of great electrical tension. In fact, these” Blackout ” have repeatedly threatened to plunge France into the dark.
In fact, there are various causes for these periods of extreme tension. But several times, we came close to a widespread blackout. The means of flexibility available to RTE are numerous, but sometimes may not be enough.
When consumption peaks occur, there is a risk of generalized cuts. In a monopoly situation, EDF had to manage these situations. However, in a liberalized market, there are several players.
It is therefore necessary to ensure on the one hand that the balance is always respected, but on the other hand that there are sufficient investments in terms of means of production over the long term.
The capacity mechanism was created precisely to solve these two problems. So first of all, we will try to understand this mechanism in detail. Then we will also see some limitations.
In order to understand the workings and the origin of this mechanism, it is necessary to delve into the recent history of the electricity sector. Indeed, as we explained in our article on” The opening of the electricity markets in France ”, the markets have completely changed in just 20 years.
We attended The appearance of new actors. These are mainly energy suppliers who are not necessarily producers. And that's where the problem starts.
In fact, formerly EDF had to plan its investments in terms of production as a single player. And that way, we could be sure that the French electricity park would continue to be maintained.
Today this certainty is no longer valid, because the economic model has changed. We are no longer certain that the French park will be up to the task. Peak periods of consumption.
In addition, there is another effect that poses this threat on the French electrical system. In fact, The energy transition pushes us to close the most polluting power plants.
For this reason, the government ordered the closure of the last Coal power plants From France for the 1Er January 2022. However, these power plants were mostly used during peak periods.
The lack of profitability was also an obstacle to the establishment of an electrical fleet for peak periods. However, in a country like France, this is essential. Indeed, the generalization of electric heating is one of the reasons that explains such tension on the networks in winter.
It is therefore for all these reasons that it was legitimate to believe that France should have a system ensuring constant investments. That's why the CRE has put in place the capacity mechanism. A system that, thanks to its operation, involves all actors in the supply of energy.
Thus, it is a question of peak periods. During these periods (often in winter, at the time of leaving the office around 18:00) the network operator must have production capacities ready to start.
To make it possible to raise the funds necessary for these investments, the mechanism urges all electricity suppliers to supply themselves in” capacity guarantees ”. They are obligated actors, like the EEC system.
Therefore, each supplier must participate in capacity guarantee auctions provided for this purpose, to purchase guarantees. Obviously, each supplier is supplied according to their real needs.
RTE decides to designate what we call PP1 days. That is, the coldest days of the year according to weather forecast data. They are announced the day before for the next day by RTE. Over a delivery year, RTE can designate between 10 and 15 PP1 days.
To estimate its need, each supplier will therefore estimate your consumption on specific hours during these PP1 days. The slots selected are as follows: [07:00 — 15:00] and [18:00 — 20:00].
This is how he deducts the amounts to be purchased at the auction. Prices can vary greatly from auction to auction, as well as from year to year. As you can see in the chart below.
Thus, each supplier must buy the equivalent of its consumption in capacity guarantees, knowing that a guarantee is equal to 0.1 MW of power. They can be purchased on the capacity market organized by EPEX Spot, or by mutual agreement from a warranty seller.
Nevertheless, an inspection is carried out by CRE and RTE. If an electricity supplier does not have enough capacity certificates in relation to its actual needs, it must pay penalties.
First of all, one of the drawbacks of this system is the complexity of implementation for suppliers. Indeed, the calculation rules, but also the participation in numerous auctions, complicate the management of suppliers.
These stones often require significant treatments and sometimes also confusion. The system also provides for the adjustment of the amounts paid the following year. This adds complexity as well as additional financial flows.
It is also difficult to be able to predict how the cost will change in the future. The multiplication of auctions and the lack of liquidity in this market make it difficult to forecast.
It is also important to remember that the additional cost induced by this system is passed on to the end customer by all suppliers. Since 2017, a “capacity mechanism” line has therefore appeared on French consumers' invoices.
However, customers equipped with a communicating meter (Linky) can nevertheless reduce this cost by modulating their consumption during these days. Erase operators can also take advantage of this mechanism.
Despite the difficulty of implementation, it is true that this mechanism can also represent an opportunity for some actors. Producers in particular, who see their capabilities certified.
Some European countries now have capacity mechanisms in place. However, there are plenty of other business models out there.
In Europe, the choice of a strategic reserve to replace our model stands out, as in Germany. Everything depends on the energy orientation of the country as well as the means of production available. As we have seen, electric heating is partly responsible for the peak in consumption. Some countries are not as sensitive to temperature changes.

.png)
Centralising the mechanism under a single buyer, RTE, aims to remove the price volatility (excluding taxes) linked to the decentralised system. That system, considered too complex, required suppliers to acquire capacity guarantees themselves. The 2026 reform gives RTE sole control of the mechanism to guarantee security of supply and stabilise the capacity costs passed on to end consumers.
.png)
The capacity cost will now be built in transparently through an allocation levy, with tight supervision of the auctions. From November 2026, the mechanism does not disappear but its billing structure changes. The aim is better control of prices excluding taxes, through price caps and reduced windfall revenues for generation assets that are already paid off.