Chevron noirChevron noir

What do the PP1 and PP2 days correspond to?

Understanding energy
Energy market
Electricity
Budget

What do the PP1 and PP2 days correspond to?

Publié le

26 June 2024

7

Min reading

An electricity pylon against an evening sky, illustrating grid strain managed by RTE on PP1 and PP2 peak days

In this article, SirEnergies introduces you to PP1 and PP2 days, periods when the voltage in the electrical system is too high and when the capacity mechanism makes it possible to secure the supply of electricity to the network.

After a simplified but relevant explanation of the capacity mechanism, the following will be discussed: the calendar of PP1 and PP2 days, the method for defining these days and what they correspond to. You will thus understand the interest for users of the electrical network of reduce their consumption Or of participate in the deletions during these peak periods.

The capacity mechanism

Originally, The capacity mechanism is a device that was created to offer additional remuneration to ultra-advanced power plants, the same ones that provide the security of electricity supply during peak periods. This mechanism therefore contributes greatly to The balance between the power drawn by consumers and the power injected by producers and erasure aggregators during episodes of high stress on the electrical system.

The capacity mechanism was put in place by the NOME law, following the report of the Champsaur Commission of 24 April 2009 which highlighted A risk of blackout in France during winter consumption peaks. Indeed, in 1999, during The opening of the electricity market For major manufacturers, only an energy market has been created.

This market, called “energy only” (EPEX Spot and Nord Pool Spot), only pays for the MWh produced by the power plants. In fact, state-of-the-art power plants that operate only a few dozen hours per year are not sufficiently paid by this market alone. This lack of remuneration has hampered investments, which has led to the erosion of extreme means of production.

To remedy this, the Champsaur Commission proposed in its report the creation of a capacity mechanism requiring all users who draw electricity from the network, the actors obliged, to reserve production or disposal capacity each year, during peak hours; this reservation being made in the form of the acquisition of capacity guarantees valid for one year.

Obligatory actors mean electricity suppliers, network operators and final electricity consumers who do not obtain all or part of their consumption from a supplier.

This mechanism, which makes it possible to pay for extreme production capacities, also offers remuneration to electrical erasure capabilities. Indeed, encouraging certain users of the electrical network to stop drawing electricity from the network, i.e. to erase their consumption from the network, either by reducing it or by producing their own electricity, has exactly the same effect as asking producers to inject more electricity into the network.

From a regulatory point of view, the capacity mechanism is codified by the articles L335-1 and following and R335-1 and following of the Energy Code. It imposes on obliged actors an obligation to have capacity guarantees in line with their anticipated energy consumption during peak days, known as PP1 days.

These capacity guarantees are exchanged, for each year of delivery, on a capacity market, EPEX Capacity, between the obligated actors on the one hand and the producers and operators of erasure on the other hand. They are required to certify their production or disposal capacity in advance for each year of delivery.

Concretely, for the obligated actor, the capacity mechanism results in the payment of a power reservation in the form of capacity guarantees proportional to the power it draws during the peak periods. Depending on whether or not he uses the services of a supplier, the obligated actor will find this amount on his electricity bill or will have to buy guarantees on the market. EPEX Capacity.

What is a PP1 or PP2 day?

PP stands for Peak Period. The days PP1 and PP2 are therefore by definition the days of peak periods of electricity consumption.

PP1 days are the days during which the average withdrawal power of each obligated actor will be measured by RTE to establish the level of obligation, and therefore the number of guarantees that it must hold.

PP2 days are the days during which erasure producers and aggregators, who have had their capacities certified by RTE, must keep them available to activate them upon request from RTE.

Every year, RTE can report 15 days PP1, which are also PP2, and 10 additional days that are only PP2. These 25 days are reported The day before for the next day, at 9:30am for PP1-PP2 days, and at 7:00pm for PP2 days only (PP2 non-PP1 days).

These days PP1 and PP2 must respect a schedule : working days from January to March and from November to December, excluding the Christmas school vacation period.

By what method are the days PP1 and PP2 defined?

To implement an optimal policy for choosing PP1-PP2 days and PP2 days only (not PP1), the method implemented by RTE is based on two criteria:

  • A consumption criterion : RTE identifies a PP1 and/or PP2 peak day by evaluating the next day's consumption the day before; for this RTE uses a model based on The weather forecast from Météo-France in order to take into account the high thermosensitivity of consumption due to the electric heating park;
  • An operational decision criterion : RTE can also declare the following day as PP2 day (not PP1) in case of identification of a significant deficit in available operating margin that increases the following day.

For the consumption criterion, the model developed by RTE uses an algorithm of inventory management in an uncertain universe that is based on use values calculated using the Bellman equation.

This algorithm is calibrated beforehand with the consumption and temperature histories. The model is then fed daily by the Météo-France forecasts for the next day, which makes it possible to execute the algorithm and calculate the consumption estimates for the following day and to deduct the risks of voltage on the electrical system. The objective for RTE is to select the days for which national consumption is highest during peak hours (7 am to 3 pm and 6 pm to 8 pm).

RTE is particularly vigilant during cold waves. Indeed, during these events, which generally occur from November to March, the temperature falls by 5°C compared to seasonal norms and can impact several regions or even the whole country for at least 3 days.

Knowing that in France, a temperature drop of 1°C in winter requires 2,400 MW of additional production; more than 12 GW are needed to deal with a cold spell in France, or 10% of the total installed production fleet.

Why were PP1 and PP2 put in place?

The establishment of the PP1 and PP2 days, and the underlying capacity mechanism, made it possible to respond in particular to two demands of alternative suppliers and to bring up to date two devices formerly implemented in regulated sales tariffs (TRV), namely:

  • Capacity pay : the subscription (in €/MW) based on the power subscribed to by the TRVs made it possible to remunerate investments in production plants and investments in networks; the former being now paid by the capacity mechanism in the form of capacity guarantees (€/MW) and the latter by the fixed component of TURP.
  • Reporting peak days : the EJP (Clear Peak Days), owned by EDF, are now finding their market equivalent with the PP1 and PP2 days determined by RTE, which allows all alternative suppliers to involve their customers in the security of supply of the system to ultimately allow them to benefit from lower billing for their electricity:
  • Or in the form of Tariff reduction, by encouraging them to reduce the power they draw from the network during PP1 days in order to reduce their obligation to hold capacity guarantees;
  • Or in the form of pecuniary gain, by certifying their erasure capacity and by involving them in erasure programs during PP2 days in order to resell on EPEX Capacity the capacity guarantees thus generated.

The PP1 and PP2 days reflect the logic of EJPs, namely: a financial incentive to extract less during peak days, EJP days that are reported the day before for the next day and counted in a monitoring calendar for the 22 EJP days; information available on the site From EDF :

The PP1 and PP2 days were set up like the EJP days in order to allow all users and producers to coordinate their efforts to strengthening the security of the electrical system and the supply of consumers.

To implement this coordination, RTE publishes PP1 and PP2 days on its service portal on a daily basis, in accordance with the principles described above, as well as Their histories.

In order to help you reduce your electricity bills, we have set up an API in order to be able to retrieve the report of the PP1 and PP2 days directly and in real time.

👇 Click on the link below to view PP1 and PP2 days for free. Consult the PP1 and PP2 peak days

If you also want to reduce your bill, do not hesitate to contact us in order to support you in this process of controlling electricity consumption.

Newsletter hebdomadaire

By Emmanuel Sire, co-founder of Sirenergies

+ 3 500

weekly newsletter subscribers

4.9

The answers to your questions

Do I need to change supplier to work with Sirenergies?

No. Sirenergies is independent of energy suppliers: we can work on your existing contracts and only recommend supplier tendering when it is in your interest.